Project scheduling, estimating, earthwork, productivity, temporary structures and construction safety.
Where to look on exam day: FE Reference Handbook: Civil Engineering (construction)
Key formulas
CPM total float
TF = LS − ES = LF − EF Activities with zero total float are on the critical path.
FE Reference Handbook: Construction (scheduling)
Earned value: cost and schedule variance
CV = EV − AC (negative = over budget) SV = EV − PV (negative = behind schedule) CPI = EV/AC, SPI = EV/PV
FE Reference Handbook: Construction (project control)
Bank, loose and compacted earthwork volumes
Loose = Bank × (1 + swell) Compacted = Bank × (1 − shrinkage)
FE Reference Handbook: Construction (earthwork)
Common traps
- Critical path: the longest path, not the shortest.
- Bank, loose and compacted volumes mixed up.
- Earned value: CV and SV use EV, not AC, as the base.
Worked example
Activities: A (3 d) and B (5 d) start the project. C (6 d) follows A. D (2 d) follows B. E (4 d) follows both C and D. What is the project duration?
- A. 11 days
- B. 13 days
- C. 15 days
- D. 20 days
Show solution
Answer: B. 13 days
Paths: A-C-E = 3 + 6 + 4 = 13 d. B-D-E = 5 + 2 + 4 = 11 d. Critical path A-C-E, 13 days.
FE Reference Handbook: Civil Engineering, Construction, CPM