Where to look on exam day: FE Reference Handbook: Civil Engineering (construction)

Key formulas

CPM total float

TF = LS − ES = LF − EF Activities with zero total float are on the critical path.

FE Reference Handbook: Construction (scheduling)

Earned value: cost and schedule variance

CV = EV − AC (negative = over budget) SV = EV − PV (negative = behind schedule) CPI = EV/AC, SPI = EV/PV

FE Reference Handbook: Construction (project control)

Bank, loose and compacted earthwork volumes

Loose = Bank × (1 + swell) Compacted = Bank × (1 − shrinkage)

FE Reference Handbook: Construction (earthwork)

Common traps

  • Critical path: the longest path, not the shortest.
  • Bank, loose and compacted volumes mixed up.
  • Earned value: CV and SV use EV, not AC, as the base.

Worked example

Activities: A (3 d) and B (5 d) start the project. C (6 d) follows A. D (2 d) follows B. E (4 d) follows both C and D. What is the project duration?

  1. A. 11 days
  2. B. 13 days
  3. C. 15 days
  4. D. 20 days
Show solution

Answer: B. 13 days

Paths: A-C-E = 3 + 6 + 4 = 13 d. B-D-E = 5 + 2 + 4 = 11 d. Critical path A-C-E, 13 days.

FE Reference Handbook: Civil Engineering, Construction, CPM