PE Civil

Construction

depth module

Depth module: earthwork, estimating, scheduling, material quality control, temporary structures and site safety.

Where to look on exam day: PE Civil Reference Handbook: Construction; OSHA 1926 and other standards NCEES lists

Key formulas

CPM total float

TF = LS − ES = LF − EF Activities with zero total float are on the critical path.

FE Reference Handbook: Construction (scheduling)

Earned value: cost and schedule variance

CV = EV − AC (negative = over budget) SV = EV − PV (negative = behind schedule) CPI = EV/AC, SPI = EV/PV

FE Reference Handbook: Construction (project control)

Bank, loose and compacted earthwork volumes

Loose = Bank × (1 + swell) Compacted = Bank × (1 − shrinkage)

FE Reference Handbook: Construction (earthwork)

Common traps

  • Float: total vs free float.
  • Formwork pressure: rate of placement and temperature both matter.
  • Crane and rigging problems: sling angle increases tension.

Worked example

At a status date, budgeted cost of work performed (EV) = $400,000, actual cost (AC) = $450,000, and planned value (PV) = $500,000. What is the cost performance index?

  1. A. 0.80
  2. B. 0.89
  3. C. 1.13
  4. D. 1.25
Show solution

Answer: B. 0.89

CPI = EV/AC = 400,000/450,000 = 0.89. The project is over budget. (SPI = EV/PV = 0.80.)

PE Civil Reference Handbook: Construction, Earned Value