Depth module: earthwork, estimating, scheduling, material quality control, temporary structures and site safety.
Where to look on exam day: PE Civil Reference Handbook: Construction; OSHA 1926 and other standards NCEES lists
Key formulas
CPM total float
TF = LS − ES = LF − EF Activities with zero total float are on the critical path.
FE Reference Handbook: Construction (scheduling)
Earned value: cost and schedule variance
CV = EV − AC (negative = over budget) SV = EV − PV (negative = behind schedule) CPI = EV/AC, SPI = EV/PV
FE Reference Handbook: Construction (project control)
Bank, loose and compacted earthwork volumes
Loose = Bank × (1 + swell) Compacted = Bank × (1 − shrinkage)
FE Reference Handbook: Construction (earthwork)
Common traps
- Float: total vs free float.
- Formwork pressure: rate of placement and temperature both matter.
- Crane and rigging problems: sling angle increases tension.
Worked example
At a status date, budgeted cost of work performed (EV) = $400,000, actual cost (AC) = $450,000, and planned value (PV) = $500,000. What is the cost performance index?
- A. 0.80
- B. 0.89
- C. 1.13
- D. 1.25
Show solution
Answer: B. 0.89
CPI = EV/AC = 400,000/450,000 = 0.89. The project is over budget. (SPI = EV/PV = 0.80.)
PE Civil Reference Handbook: Construction, Earned Value